Quartz creek bridge

Colas Company Involved: Terus

Location: Quartz Creek, BC

Client: British Columbia Ministry of Transportation and Infrastructure

This project was tendered in early 2021 with Colas company Terus being successful on the crushing, ready mix supply & paving works as a subcontractor to Pennecon Heavy Civil Ltd. For the paving scope, work began with temporary patching in 2021/2022 and permanent bottom lift and middle lift in 2023. In 2024 the remaining bottom lift and all top lift was completed. Overall scope is 39,000T of paving, 16,000T completed in 2023 with the remaining 26,000T to completed in the summer of 2024.